Bath, Steuben County · Meridian Grid Development · Docket 23-F-0264
The largest project in the pilot: 220 MW of solar with a 60 MW / 240 MWh battery across 1,620 acres in Bath and Urbana. Four municipalities have filed local law waiver challenges.
Developer
Meridian Grid Development
Location
Bath, Steuben County
Capacity
220 MW + 240 MWh
Docket
23-F-0264
Next milestone
Jul 8, 2025
Risk score
Opposition intensity 76/100 across 4 tracked actors and 7 filed documents.
Open response plan →Meridian Grid Development
1,620 acres across two towns; the largest 94-c filing in the Southern Tier to date.
Towns of Bath, Urbana, Wheeler, Avoca
Coordinated filings using shared counsel; each cites a 2023 setback law adopted after the application.
NYS ORES
Found the 1,500 ft standard would eliminate 91% of the buildable area; waiver granted in part.
Steuben County Safety Alliance
Campaign pivoted from farmland to fire risk within three weeks of the ORES ruling.
Meridian Grid Development
Battery block relocated 2,400 ft from the nearest residence with a dedicated access road.
ORES Administrative Law Judge
Issues for adjudication: emergency response capacity and cumulative agricultural impact.
Dominant framing
Fire / Battery Safety accounts for 32% of statements on this docket — hover a category for the counter-framing note.